Update letter on the proposed Shetland and Western Isles electricity...

This letter provides an update on the proposed Shetland Isles and Western Isles electricity transmission projects including an update on the anticipated timing of our decisions.

View Article



Orkney transmission project – Conditional decision on Final Needs Case

This document outlines our decision to conditionally approve a transmission link to Orkney, subject to certain conditions being met by December 2021.

View Article

Update on the Western Isles transmission project and potential next steps

This letter provides an update on the current Final Needs Case for Scottish Hydro Electric Transmission’s (SHE-T) proposed project to build a 600MW electricity transmission link between the Western...

View Article

Update on the Shetland Isles transmission project and potential next steps

This letter provides an update on the current Final Needs Case for Scottish Hydro Electric Transmission’s (SHE-T) proposed project to build a 600MW electricity transmission link between the Shetland...

View Article

Decision on Scottish Hydro Electric Power Distribution’s proposals to...

This letter sets out our decision in principle on proposals by Scottish Hydro Electric Power Distribution (SHEPD) to contribute financially towards proposed electricity transmission links to Shetland,...

View Article


Shetland transmission project: Consultation on proposed Final Needs Case and...

This consultation document sets out our views and proposals on the Final Needs Case for the Shetland transmission link project and delivery model.Stakeholders wishing to respond to our consultation...

View Article

Decision on the Final Needs Case for the Shetland electricity transmission...

This letter sets our our decision to approve the 600MW High Voltage Direct Current (HVDC) subsea transmission link between mainland Scotland and the Shetland Isles, proposed by Scottish Hydro Electric...

View Article

Update on decision to approve SHEPD's propossed methodology to...

This letter confirms that the conditions attached to our December 2019 decision to approve SHEPD’s proposed methodology for making a financial contribution to SHE Transmission’s Shetland transmission...

View Article


Shetland transmission project: Decision on Final Needs Case and Delivery Model

Further to confirmation on 16 July 2020 of our conditional approval of the Final Needs case, this document confirms our decision on the Final Needs Case for Scottish Hydro Electric Transmission’s...

View Article


Orkney transmission project – May 2021 update

In March 2021 Orkney developers requested a twelve-month extension to the deadline for meeting our conditions of approval for the Orkney transmission project. This update sets out the reasons for our...

View Article